AmerenUE Meramec Power Plant, Boeing Track II,
Holcim, Chrysler, Pfizer
Pfizer Global Research & Development
CV SUMP Generator & Power Distribution | Chesterfield, MO
Like replacing a car engine while it was running - the electrical upgrade at Pfizer's Chesterfield campus was so complex that two pre-qualified electrical contractors declined to bid the work. PayneCrest accepted the challenge and more than doubled the power capabilities of the campus to support - without disrupting - Pfizer's expansion of its pilot production of biologic drugs for clinical trials.
PayneCrest also diligently worked with two Pfizer consultants hired to oversee stringent design and installation requirements endemic to the pharmaceutical industry. In the end the 10-month long project was completed on time, within budget and without a single unplanned outage.
|